ATTENUATION TANKS AT DOHA METRO STATIONS

Water Infrastructure

Doha, Qatar

As part of the Qatar Integrated Rail Project, the construction of reinforced concrete Storm Water Underground Attenuation Tanks in the Gold Line Metro.

Stations were awarded to ADMC.

Works executed include:

  1. Structural works.
  2. Steel Fixing of all sizes including placing of the spacer, coupler.
  3. Formworks procurement, installation, and dismantling.
  4. Concreting Works.

Project Details

DATE

AUGUST 2018 – OCTOBER 2018

CLIENT

Aktor-L&T- Yapi Merkezi-Stfa-AL Jaber Engineering (Alysj JV)

PROJECT TYPE
CONTRACTOR

ADMC International